What You’ll Need Before You Start
Most homeowners start the planning permits process backwards, drawing up what they want before checking whether the council will allow it, the biggest cause of delays, rejected applications, and expensive redesigns.
This guide from PBS Carpentry & Maintenance Services & Home Extensions Melbourne breaks the process into practical steps: what to lodge, when to expect a decision, and what happens if something goes wrong.
Before lodging anything for a planning permit, pull together five things:
- A current copy of your property’s title, including any covenants or easements
- Your local council’s planning scheme map for your address
- A site plan showing boundaries, existing structures, and proposed works
- A brief written description of what you want to build and why
- A rough budget that includes council fees, consultant costs, and a contingency
Get these wrong and you’ll be answering a request for further information before you’ve even started.
Do You Need a Planning Permit or Building Permit?
A planning permit is council approval for how land is used and developed, setbacks, height, heritage impact, neighbourhood character. A building permit is separate approval confirming the construction meets structural, safety, and energy standards. Many projects need both; one does not replace the other.
Here’s the trap: assuming a building permit is all you need because a builder said so. If your property sits in a heritage overlay, a Design and Development Overlay, or a Vegetation Protection Overlay, you may need a planning permit even for minor works. Check your planning scheme before committing to a design.
Planning Permit Application Checklist
The checklist below covers what most Victorian councils ask for. Requirements vary by council and application type, so confirm against your own council’s published checklist before lodging. The notes explain why each item matters, a document that exists but does not answer the planning question is the same as not supplying it.
- Completed application form for your council, including the section on how the proposal responds to the planning scheme. Vague answers here are a common trigger for a request for further information.
- Certificate of Title (no older than 60 days in most cases), this reveals covenants, easements, and restrictions that can override what the planning scheme would otherwise allow.
- Site plan at the required scale, showing all boundaries, dimensions, existing structures, and proposed works. North point and levels are usually mandatory.
- Floor plans and elevation drawings of the proposed development, dimensioned and to scale.
- A written report explaining the proposal and how it responds to the planning scheme, including any relevant overlays and local policy.
- Photographs of the site and surrounding properties, including streetscape context.
- Specialist reports required by overlays, a heritage assessment, arborist report, land survey, drainage or stormwater plan, or traffic assessment depending on what applies.
- The correct application fee, paid at lodgement.
Overlay Triggers That Change the Checklist
Generic checklists fail here: the same extension can require a very different document set depending on your overlays.
- Heritage Overlay (HO): expect a heritage impact statement, and often a conservation management plan for significant buildings. Council will assess whether the works are reversible and whether they respect the original fabric.
- Design and Development Overlay (DDO): may impose mandatory height, setback, or built-form requirements. A written design response addressing each DDO schedule is usually expected.
- Vegetation Protection Overlay (VPO) or Significant Landscape Overlay (SLO): an arborist report and a tree management plan are typically required before any removal or works near protected vegetation.
- Special Building Overlay (SBO) or Land Subject to Inundation Overlay (LSIO): a flood level report and sometimes a referral to the relevant water authority, which adds its own timeframe.
- Development Plan Overlay (DPO): the proposal must be consistent with an approved development plan, which can add a layer of assessment before the permit itself is considered.
Check your overlays on the VicPlan mapping tool or your council’s planning scheme map before commissioning drawings. Designing first and discovering an overlay later is the most expensive sequencing error in this process.
Lodging an incomplete application does not speed things up. Councils will issue a request for further information, and the statutory clock often stops until you respond, which can add weeks to your timeline.
Responding to a Request for Further Information (RFI)
An RFI is the most common point where applications stall, so treat the response as a project in itself:
- Read the RFI against the planning scheme. Each item usually maps to a specific clause, overlay, or policy; understanding why it was asked lets you answer the actual concern rather than just supplying a document.
- Build a response tracker. List every item, who is responsible (you, your designer, an arborist, a surveyor), and the date it was sent. Nothing should sit unassigned.
- Send one consolidated response where possible. Multiple partial responses reset the assessment and frustrate the planner.
- If an item will take time, write to the council and give a realistic date rather than going silent. Silence is read as abandonment.
- Keep proof of submission, a dated email or portal receipt. If a dispute about timing arises later, this is your evidence.
Before lodging, ask your designer or draftsperson to run a self-check against the council’s published checklist and the relevant overlay schedules. Catching a missing arborist report or heritage statement at this stage costs days; catching it after an RFI costs weeks.
Step-by-Step: How to Lodge a Planning Permit Application
Lodging a planning permit application in Victoria follows a defined sequence, and the right order saves weeks. Most councils accept online lodgement through their planning portal; some still require hard copies.

- Confirm permit requirements. Check your planning scheme and overlays, or call your council’s planning department to confirm what applies to your address.
- Prepare your supporting documentation. Assemble the checklist items above before you lodge, not after.
- Complete the application form. Answer every question, including the section on how your proposal responds to the planning scheme.
- Pay the application fee. Fees are set by the relevant regulations and vary by council and project type; check your council’s current fee schedule.
- Lodge and track. Submit online or in person, keep your receipt and reference number, and note the lodgement date.
- Respond to any requests promptly. If council issues a request for further information, treat it as your top priority.
Responding to a Request for Further Information
A request for further information is a formal notice from council asking you to supply missing or additional detail before your application can be assessed. It is not a rejection, but it is the most common point where applications stall, and how fast you respond affects your timeline.
Build a response tracker: each item requested, who is responsible (you, your designer, or a specialist), and the date sent. Send everything in one response where possible and keep proof of submission. If an item will take time, tell the council in writing rather than going silent.
How Long Does a Planning Permit Take in Melbourne?
A planning permit application in Victoria is subject to a statutory timeframe: for most standard applications, council has 60 days from receiving a complete application to decide (planning.vic.gov.au). That clock pauses when council requests further information, and excludes your preparation time.
In practice, straightforward applications without overlays move faster, while heritage or design-sensitive proposals, or ones attracting objections, take longer. If your project must finish before a particular season, work backwards from that date and allow buffer for the RFI stage. This is exactly the timeline question homeowners often have before a renovation begins.
The Planning Permit Objection Process
The planning permit objection process allows neighbours and affected parties to formally object. Once council receives your application, it decides whether public notification is required. For most applications affecting neighbours, new dwellings, extensions, subdivisions, many commercial proposals, notification is standard.
How Notification Works
Notification usually involves a combination of:
- A sign on the site, visible from the street
- Written notice to nearby and adjoining property owners and occupiers
- A notice in the local newspaper for some application types
The notice sets a closing date for objections, commonly 14 days from the date of notice, though this can vary (planning.vic.gov.au). Objections must be in writing and lodged before that date. Late objections are generally not considered.
What Makes a Valid Objection
Council assesses objections on planning grounds, that is, matters the planning scheme actually allows it to consider. Strong grounds typically include:
- Overshadowing of habitable rooms or private open space
- Overlooking and loss of privacy
- Visual bulk and inconsistency with neighbourhood character
- Traffic, parking, and access impacts
- Noise, odour, or amenity impacts
- Inconsistency with the planning scheme, overlays, or local policy
- Heritage impact on a significant building or precinct
Objections based on personal dislike, design style, or the fact a development is happening at all carry little weight. A well-written objection cites the relevant planning scheme clause and explains the specific impact, ideally with photographs, shadow diagrams, or a traffic assessment.
If You Are the Applicant and Receive an Objection
An objection does not automatically stop your project. Council can still approve it, often with conditions addressing the objection, a screening requirement, reduced height, or changed setback. The practical options:
- Respond in writing to the objection, addressing each planning ground raised
- Offer a negotiated amendment to the plans that resolves the concern without gutting the project
- Attend a council-run mediation or consultation meeting, where one is offered
- Proceed to a council decision, accepting that a refusal may follow and that review rights then apply
A common pattern: a single well-founded objection, usually overshadowing or overlooking, is resolved by a modest design change the applicant would have accepted anyway. Addressing it early is almost always cheaper than fighting it.
Third-Party Review Rights
If council grants a permit and an objector is dissatisfied, the objector may apply to the Victorian Civil and Administrative Tribunal (VCAT) for a review. Not every objector has standing, and strict time limits apply, generally 28 days from the decision notice (vcat.vic.gov.au). If council refuses, the applicant can also seek a review. Missing a deadline can end the matter, so diarise the date the decision notice arrives.
Objections are rarely about winning or losing outright. They are about whether the planning scheme’s concerns have been addressed. An applicant who treats an objection as a design problem to solve, rather than a fight to win, usually gets a better and faster outcome.
Appeals, Compliance, and What Happens After Approval
An approval is not the finish line. Once council issues a decision notice and your permit, the endorsed plans become the legally binding version of your project. Build something different and you are in breach.
If council refuses your application, or you disagree with a condition, you can apply for a review at the Victorian Civil and Administrative Tribunal (VCAT) within the statutory appeal period. Objectors can also seek a review of a decision to grant a permit. Deadlines are strict, diarise them the day the decision notice arrives.
After approval, keep these obligations on your radar:
- Build strictly to the endorsed plans
- Comply with every permit condition, including any time limits on when works must start and finish
- Apply for an amendment if you need to change the approved plans
- Request written confirmation of compliance once works are complete, if your permit requires it
Photograph each stage of construction as it progresses. If a compliance question arises later, dated photos of the works matching the endorsed plans are far more useful than memory.
Hiring a consultant versus managing the application yourself comes down to complexity. For a simple proposal with no overlays, a well-prepared DIY application can work. For heritage properties, significant extensions, or anything likely to attract objections, a town planning consultant or an experienced builder who manages the process end to end usually saves more time than they cost.
Managing a planning permit is rarely about the paperwork itself. It is about anticipating what council will ask, responding fast, and building to exactly what was approved. Get those three right and the process stays predictable.
At PBS Carpentry & Maintenance Services & Home Extensions Melbourne, we handle comprehensive renovation services, serving homeowners seeking to enhance their living spaces and increase property value. Our dedicated and expert team provides a personalised approach from initial design to final construction, ensuring every project is tailored to your specific needs for seamless house renovations. We stand out by consistently delivering exceptional craftsmanship, competitive pricing, and timely project completion, adding lasting value and beauty to your home. If you are planning an extension or renovation and want the approval and build handled as one seamless process, get a quote and let’s map out your project.
Frequently Asked Questions
Who issues planning permits in Victoria?
Your local council issues planning permits through its town planning department. Each council assesses applications against the relevant planning scheme, which sets out zoning, overlays, and local policies. Some larger developments may be assessed by the Minister for Planning or a specified responsible authority. Before lodging, confirm which council covers your property and whether any planning overlays apply, because these determine what you can build and what supporting documentation you need to submit.
What is the difference between a planning permit and a building permit?
A planning permit covers land use and development: whether your proposal suits the site, zoning, and neighbourhood character. A building permit covers construction standards: structural adequacy, safety, and compliance with the Building Regulations 2018 and the National Construction Code. Many projects need both. You usually obtain planning approval first, then apply for a building permit through a registered building surveyor before any demolition or construction begins.
How long is a planning permit valid in Victoria?
Most planning permits in Victoria stay valid for two years from the date of issue, though conditions on your decision notice may specify a different period. If you have not started the approved development within that timeframe, the permit lapses and you may need to apply for an extension before it expires. Starting works usually means more than site preparation. Check your permit conditions carefully and diarise the expiry date so you do not lose your approval.
Can I see my neighbour’s building plans in Victoria?
Yes, during the public notification period. When a council advertises a planning application, nearby owners and occupiers can inspect the plans and supporting documents, often via the council’s planning register or at the council offices. You can then lodge an objection within the stated timeframe if you believe the proposal causes unreasonable amenity impacts. Once the notification period closes, access to plans may be limited, so act promptly if you want to review or object.